丰满水电站重建工程坝基主要地质缺陷处理设计  被引量:2

Design of treatments on main geological defects of dam foundation of Fengman Hydropower Station Reconstruction Project

在线阅读下载全文

作  者:郭建业[1] 尹洪强 郝利勋[1] 银佳男 GUO Jianye;YIN Hongqiang;HAO Lixun;YIN Jianan(China Water Northeastern Investigation Design and Research Co.,Ltd.,Changchun 130021,Jilin,China)

机构地区:[1]中水东北勘测设计研究有限责任公司,吉林长春130021

出  处:《水利水电技术(中英文)》2020年第S02期153-157,共5页Water Resources and Hydropower Engineering

摘  要:丰满水电站重建工程坝基基岩为变质砾岩,岩质坚硬,抗风化能力强。但坝基断裂构造较发育,断层数量多且较为密集,断层之间纵横交错并相互切割,导致坝基岩体较破碎、完整性差,对大坝稳定、应力及不均匀变形等均带来不利影响。设计针对坝基开挖揭露的各种地质缺陷进行了加固处理,使其满足了本工程的建坝要求,保证了工程的安全和质量。The dam foundation bedrock of Fengman Hydropower Reconstruction Project consists of metaconglomerate with hard property and strong weathering resistance.However,the fracture structure of the dam foundation is more developed with more and dense faults,while the faults are criss-crossed and cross-cut each other,which make the dam foundation rock mass more broken with poor integrity and bring about unfavorable impacts on the stability of dam,stress,uneven deformation,etc.Targeting at all kinds of the geological defects exposed therein during the excavation of the dam foundation,the relevant reinforcing treatments are designed,and then the requirements of the dam construction for this project are satisfied,thus the safety and quality of the project are ensured as well.

关 键 词:碾压混凝土重力坝 坝基 地质缺陷 加固处理 

分 类 号:TV642.3[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象