赵楼矿深厚表土层冻结法凿井工程监测技术  被引量:5

Monitoring and measurement technology for mine shaft freezing sinking project of Zhaolou Mine in deep thick overburden

在线阅读下载全文

作  者:邵景柱[1] 吕树杰[1] 王伟 宋雷[2] 

机构地区:[1]兖煤菏泽能化有限公司赵楼矿,山东郓城274705 [2]中国矿业大学建筑工程学院

出  处:《煤炭科学技术》2008年第2期33-38,共6页Coal Science and Technology

摘  要:结合赵楼矿深厚表土冻结法凿井工程,介绍了冻结法凿井中的地层冻结工程相关参数监测、井帮温度与变形监测和井壁收敛监测、上部已成型井壁段的温度和受力与变形监测,依据监测结果及其规律分析,主井及时中途套壁,副井在出现井壁裂隙的情况下坚持大段高掘砌。赵楼矿主副井外壁掘砌平均速度分别为88.33 m/月和93.21 m/月,内壁套砌速度均超过280 m/月。两井筒施工与施工组织设计相比分别提前28 d和26 d通过冻结段,节约直接冻结运行费约396万元,实现了深厚表土冻结法凿井的安全、快速施工。In combined with the mine shaft freezing sinking project in deep thick overburden of Zhaolou Mine,the paper introduced the data monitoring and measurement,mine shaft wall temperature and deformation monitoring and measurement,mine shaft linear convergence monitoring and measurement,the temperature,stressed and deformation monitoring and measurement of the top section shaft linear related to the ground freezing project of the freezing shaft sinking.According to the monitoring and measure results and the law ...

关 键 词:深厚表土 冻结法 凿井 工程监测 

分 类 号:TD265.3[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象