输气管道穿河段水工保护工程埋深问题探讨  被引量:5

Discussion on Depth of Foundation to Hydraulic Protection Project for River Crossing in Gas Transportation Pipeline Construction

在线阅读下载全文

作  者:宿星[1] 杨涛[1] 郭定一[1] 吴玮江[1] 陈瑾[1] 

机构地区:[1]甘肃省科学院地质自然灾害防治研究所,甘肃兰州730000

出  处:《甘肃科学学报》2008年第4期78-81,共4页Journal of Gansu Sciences

摘  要:以"涩宁兰输气管道巴音河穿越段水工保护工程"为实例,采用管道河流穿越工程中广泛应用的冲刷经验公式,对该穿越段的冲刷深度进行计算,通过对比分析各计算结果的合理性与可靠性,提出了符合实际情况的水工保护工程基础埋置深度,为油气输送管道穿越段水工保护工程设计与工程基础埋深的确定提供了技术参考和较可靠的科学依据.Taking Bayin River Crossing as an example,which is only a sechis of Hydraulic Protection Project for Sebei-Xining-Lanzhou Gas Transportation Pipeline,we have calculated the depth of scour in this section by using the scouring empirical formulae that have been widely used in the pipeline engineering.We have analyzed the reliability and appropriateness of the calculated results.On this basis,we put forward the depth of foundation to the hydraulic protection project according with the actual situation,thus pro...

关 键 词:涩宁兰输气管道 穿越工程 水工保护工程 冲刷深度 基础埋深 

分 类 号:TE973[石油与天然气工程—石油机械设备]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象