作 者:叶彩娟[1]
机构地区:[1]中铁第一勘察设计院集团有限公司,西安710043
出 处:《铁道标准设计》2012年第6期11-15,共5页Railway Standard Design
摘 要:包西铁路在柳树店段受地形及既有建筑物的影响,改线后遇见黄土高边坡挖方工程,采用明洞通过。为避免施工过程中边坡塌方及解决明洞的偏压问题,采用路堑桩板墙与明洞工程相结合的方案,用桩板墙工程代替明洞工程抵抗左侧山体变形而形成的偏压,保证了施工过程边坡的稳定。The opencut tunnel with high side slope of loess was adopted in Liushudian section of Baotou-Xi'an Railway.To avoid side slope collapse during construction and to solve the problem of eccentric compression on the opencut tunnel,the scheme of sheet pile wall on the cutting in combination with the opencut tunnel was utilized.It is considered that instead of the opencut tunnel,the sheet pile wall can resist the eccentric compression caused by the deformation of the slope mass on the left side,so the stability of side slope during construction can be guaranteed.
分 类 号:U213.1[交通运输工程—道路与铁道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.222