检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
作 者:王海涛[1]
机构地区:[1]西安热工研究院有限公司,陕西西安710032
出 处:《热力发电》2012年第11期59-63,66,共6页Thermal Power Generation
摘 要:介绍了印尼INDRAMAYU电站330MW机组快速甩负荷(FCB)试验的过程,在分析了FCB过程中出现的旁路保护误动、汽轮机转速超调、主蒸汽温度大幅下降等问题的基础上,对高压旁路减温控制回路参数、FCB时汽轮机联锁发电机跳闸控制逻辑等进行了优化。优化后的FCB试验结果表明,主蒸汽、再热蒸汽下降最大温差分别为25℃和23℃,控制系统的调节品质显著提高。Several fast cut back(FCB) tests of the 330 MW unit in Indonesia INDRAMAYU Power Plant were presented.Based on analyzing such problems as wrong action of bypass protection system,speed overshoot of the turbines,and sharp decrease of the main steam temperature,optimization of parameters of temperature regulation control loop in high pressure bypass and generator tripping control logic of steam turbine interlocking during FCB was performed.Test results showed that,the maximum differences of temperature main and reheat steam drop for were 25 ℃ and 23 ℃,respectively.After the improvement,the regulation quality was significantly enhanced.
关 键 词:330 MW机组 FCB 汽轮机 旁路系统 转速 主蒸汽温度
分 类 号:TK323[动力工程及工程热物理—热能工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.3