作 者:ZHONG DengHua1, REN BingYu1, LI MingChao1, WU BinPing1 & LI MingChuan2 1 Department of Hydraulic and Hydroelectric Engineering, School of Civil Engineering, Tianjin University, Tianjin 300072, China 2 Ertan Hydropower Development Company, Ltd., Chengdu 610051, China
出 处:《Science China(Technological Sciences)》2010年第10期2611-2618,共8页中国科学(技术科学英文版)
基 金:supported by the National Basic Research Program of China("973"Project)(Grant No.2007CB714101);the National Key Technology R&D Program in the11th Five-year Plan of China(Grant No.2008BAB29B0501);the National Natural Science Foundation of China(Grant No.90815019)
摘 要:A complete scheme for solving the key scientific problems associated with high-standard,high-intensity continuous construction of high arch dams was presented. First,based on a coupling analysis of construction system decomposition and coordination for a high arc dam,a mathematical model for real-time control of construction quality and progress that considers complex constraints was developed. Second,a method of progress control was proposed based on a dynamic simulation. Third,a dynamic quality control mechanism was established based on construction information collected using a PDA. Fourth,a system for integrating collected information,progress simulation and quality control analyses under a network environment was developed. Finally,these methods were applied to a practical project to show that each aspect of a construction process can be managed effectively and that real-time monitoring and feedback control can be realized. Our methods provide new theoretical principles and technical measures for quality and progress control in the high arc dam construction process.A complete scheme for solving the key scientific problems associated with high-standard,high-intensity continuous construction of high arch dams was presented. First,based on a coupling analysis of construction system decomposition and coordination for a high arc dam,a mathematical model for real-time control of construction quality and progress that considers complex constraints was developed. Second,a method of progress control was proposed based on a dynamic simulation. Third,a dynamic quality control mechanism was established based on construction information collected using a PDA. Fourth,a system for integrating collected information,progress simulation and quality control analyses under a network environment was developed. Finally,these methods were applied to a practical project to show that each aspect of a construction process can be managed effectively and that real-time monitoring and feedback control can be realized. Our methods provide new theoretical principles and technical measures for quality and progress control in the high arc dam construction process.
关 键 词:CONSTRUCTION quality CONSTRUCTION PROGRESS dynamic simulation real-time control network HIGH ARC DAM
分 类 号:TV642.4[水利工程—水利水电工程] TV512