X70钢管道冬季焊接和防腐的技术措施  被引量:1

Technical Measures for Winter Construction of X70 Steel Pipes

在线阅读下载全文

作  者:张存华[1] 张海力[1] 张明瑾[1] 张世梅[1] 

机构地区:[1]中国石油天然气管道局,河北廊坊065000

出  处:《石油工程建设》2009年第S2期110-112,1,共4页Petroleum Engineering Construction

摘  要:在兰银管道工程建设中,通过认真研究和大量的实践,总结出了一套有效的X70钢管道冬季焊接和防腐的技术措施,包括焊前预热、焊接中防风保温、焊后和返修保温缓冷、补口作业的除湿和保温等,给今后管道工程高强钢管的冬季焊接和防腐施工提供了借鉴。Through deepening research and large amounts of practical work,a set of technical measures of welding and anticorrosion for winter construction of Lan-Yin Pipeline are summarized including preheating before welding,wind-proof and heat preservation during welding,heat preservation and cooling delay after welding and during repair,dehumidifying and thermal insulation for field joint.This experience provides a reference for future winter welding and anticorrosion constructions of X70 high strength steel pipes.

关 键 词:X70钢 焊接 保温 防腐 冬季施工 

分 类 号:U175[交通运输工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象