出 处:《安徽电力》2013年第S1期25-28,共4页Anhui Electric Power
摘 要:为验证1 000 kV淮上线特高压工程用人字抱杆在不同受力条件下的稳定性;特进行人字抱杆荷载试验,为淮上线杆塔以及长江大跨越锚塔施工措施提供试验依据。根据试验结果,分析优化人字抱杆连接结构,确保准上线杆塔组立施工安全,并为以后应用人字抱杆协助立塔施工提供教术支持。In onler to verify the stability of 1 000 kV UHV Anhui-Shanghai transmission line project with herringbone derrick under different stress conditions,specially herringbone derrick load test was carried out,for the Anhui-Shanghai transmission line pole and tower and the Changjiang river long- span anchor tower construction measures were provided experimental basis.According to the testing results,the paper analyzes the optimization of herringbone derrick connecting structure,ensure the Anhui-Shanghai transmission line pole and tower erection construction safety,and provide technical support for future application of herringbone derrick assist tower construction.
关 键 词:1000 kV淮上线特高压 杆塔组立 人字抱杆 荷载试验
分 类 号:TM752[电气工程—电力系统及自动化]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.33