C40水下不分散混凝土在漫湾电站水垫塘修补中的应用  

Application of C40 Anti-washout Underwater Concrete in Reparation of Water Bed Pond at Manwan Power Station

在线阅读下载全文

作  者:何苏华[1] 周伟 

机构地区:[1]铁道部第四设计勘探研究院监理公司,湖北武汉430063 [2]中国石油集团工程技术研究院,天津塘沽300451

出  处:《石油工程建设》2004年第5期13-14,共2页Petroleum Engineering Construction

摘  要:采用吊罐法对厚50cm左右、最小面积5~10m2的水下不分散混凝土修补工程进行施工,在国内鲜有报道。通过漫湾电站C40水下不分散混凝土工程实例,介绍了C40水下不分散混凝土修补材料的配比、施工工艺和技术要点。实践表明:用C40水下不分散混凝土代替聚合物混凝土施工,降低了工程造价,保证了工程质量。对类似的水下混凝土工程的施工,具有很好的指导意义。It is the rare case being reported at home to use anti-washout underwater concrete in reparation construction. This paper introduces the mix proportion of reparation materials, construction process and technological points of C40 anti-washout underwater concrete through the engineering example of Manwan Power Station. The practice shows that the substitution of C40 anti-washout underwater concrete for polymer concrete will reduce engineering cost and ensure engineering quality. It provides a good guidance for similar anti-washout underwater concrete projects.

关 键 词:水下不分散混凝土 修补施工 材料配比 工艺 技术要点 

分 类 号:TV431[水利工程—水工结构工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象