240m高烟囱双钢内筒顶升倒装施工工艺  被引量:1

A 240m chimney with interior double steel shaft constructed by the hydraulic reversible liftingmethod technology

在线阅读下载全文

作  者:王立群 

机构地区:[1]上海电力建筑工程公司

出  处:《建筑技术》1993年第2期103-105,共3页Architecture Technology

摘  要:上海市石洞口第二电厂高240m钢筋混凝土外筒、双钢内筒烟囱采用自爬式液压顶升倒装施工工艺,取得了58d完成1号钢内筒顶升工作的高速度和钢内筒中心偏差+3.47m、相对倾斜偏差1/6900的高质量,施工技术达到国际先进水平。A 240m chimney with exterior R. C. shaft and interior doublesteel shaft has been well con- structed by the bydraulic self-climbing and reversible lifting method. The whole construction work has been finished completely within 58 days. And its No. 1 interior steel shaft's lifting work has been done with high speed efficiency. Besides, it is to be noted that the shaft's central deviation is merely +3. 47ram, while its relative slant deviation is only 1/6900. Therefore, it is generallyrecognized as a high quality job and up to the standard of international level.

关 键 词:烟囱 液压顶升 倒装法 施工工艺 

分 类 号:TU761.2[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象