向家坝水电站纵向围堰堰脚冲刷可靠性分析  被引量:3

Reliability analysis on the toe scouring of longitudinal cofferdam for Xiangjiaba Hydropower Station

在线阅读下载全文

作  者:肖群香[1] 胡志根[1] 刘全[1] 

机构地区:[1]武汉大学水资源与水电工程科学国家重点实验室,湖北武汉430072

出  处:《水力发电》2005年第2期29-30,43,共3页Water Power

基  金:国家自然科学基金项目(50079017)

摘  要:在由能量方程及临界受力平衡方程得到块石起动流速公式的基础上,系统分析了影响围堰堰脚冲刷的主要因素,以及河道来流不确定性与块石起动不确定性之间的关系。运用可靠性理论,以河道来流流速超过块石抗冲流速的概率来刻画堰脚冲刷风险,提出了纵向围堰堰脚冲刷的可靠性模型,给出了冲刷风险率Monte-Carlo计算方法。通过对向家坝水电站物理模型试验结果的对比分析,说明理论计算模型和方法是有效的、可行的。Based on the incipient velocity of rubble derived from the strength balance and energy equation of mobile sands the dominating factors affecting the toe scouring of longitudinal cofferdam are systematically discussed and the relation of uncertainties between the construction flood and incipient velocity of rubble is analyzed. Then the application of the dependability theory an erosion reliability model of rubble on the toe of cofferdam is erected in which the erosion risk is measured by the probability that current velocity of river way exceeds incipient velocity of rubble. And Monte Carlo method is put forward for computation. Comparing with the physical model test data of Xiangjiaba Hydropower Station it showed that the reliability model and computation method are reasonable and effective.

关 键 词:施工导流 围堰稳定 抗冲流速 可靠性分析 MONTE-CARLO方法 向家坝水电站 

分 类 号:TV551.3[水利工程—水利水电工程] TB114.3[理学—概率论与数理统计]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象