马迹塘水电站病坝治理  

Treatment of Majitang Hydropower Station sick dam

在线阅读下载全文

作  者:聂广明[1] 曹希尧[2] 曹胜前 

机构地区:[1]国家电力公司大坝安全监察中心,浙江杭州310014 [2]湖南省电力公司,湖南长沙410007 [3]马迹塘水电厂,湖南桃江413405

出  处:《水力发电》2005年第1期77-79,共3页Water Power

摘  要:马迹塘水电站建设初期为地方项目,由于资金等原因,建设过程中取消了大坝23孔泄洪闸的检修闸门,致使其弧形工作门在20多年的运行过程中无法检修,同时厂房3号机组坝段基底拉应力也不能满足规范要求,大坝安全存在较大隐患。首次定期检查后,该坝被国家电力公司审定为病坝。在消缺处理过程中,又发现坝基、坝前严重淘刷。病坝治理过程艰难复杂,施工条件苛刻,技术难度大,前后历时5年,投入资金1300多万元,终于完成了治理。其经验可供其他工程参考。The preliminary construction of Majitang Hydropower Station is a provincial subject and because of financial problem, no 23 spillway bulk head gate setting was cancelled, therefore the redial gate could not be overhauled for 20 years during operation, meanwhile foundation tensile strength of No 3 unit bay could not meet the requirements of standard. After the first periodic inspection, the state power corporation assesses that the dam is sick. The incaving of foundation and upstream facing was serious. The treatment of the project was very complicated, rigorous construction condition and lofty construction techniques were required. After 5 years' hard work and investment of more than 13 million Yuan, the treatment was completed ultimately. The experience can be a excellent reference to other project.

关 键 词:病险坝 除险加固 马迹塘水电站 

分 类 号:TV698.23[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象