浅析竖井施工中井颈下沉及矫正  

Simple analysis of the drop-down of mine-shaft neck and its rectification

在线阅读下载全文

作  者:杨正全 

机构地区:[1]山东省新城金矿

出  处:《黄金》1995年第12期15-18,共4页Gold

摘  要:新城金矿主竖井施工中发生井颈钢筋混凝土下沉,采用在井颈钢筋混凝土下面用临时钢管加砖垛支撑,短掘短砌的施工方法进行矫正,达到了部颁验收标准。这种施工方法值得在今后竖井施工中借鉴。Due to drop-down of the reinforced concrete of mine-shaft neck took place during constructing main shaft in Xin-Cheng Gold Mine, the steel tubes and brick piles were laid under the dropped reinforced concrete to support it temporarily and a construction method of short-range excavating and brick laying was employed to make the dropped mine-shaft neck rectified.By doing so, the construction of mine-shaft in this gold mine was up to the criterion issued by M.M.I.The author believes that this method can be used in other mines for reference.

关 键 词:竖井 施工 井颈 下沉 矫正 金矿 

分 类 号:TD262.11[矿业工程—矿井建设]

 