李家峡水电站导流洞进口洞脸边坡处理及进洞措施  被引量:1

Side slope treatment of Lijlaxia diversion tunnel and measures to start tunnelling

作  者:姚福海[1] 任明轩[1] 春光魁[1] 

机构地区:[1]西北勘测设计研究院

出  处:《水力发电》1995年第6期51-54,共4页Water Power

摘  要:李家峡水电站导流洞进口,地势陡峭,坡面自然高度达200余m。高程2130m平台以下为85m高的洞脸边坡,该部分坡积物清除完后,意外地出现了NS向及NE向两组密集度很高的构造裂隙。这两组裂隙与岩层相互切割形成的不稳定体导致提前进洞失败。因此,如何在裂隙极为发育的薄层混合岩边坡上成洞便成了工程前期的头号技术难题。The upstream side of the diversion tunnel in Lijiaxia Hydropower Station is a steep slope with a height of 200m. Below the terrace with an elevation of 2130m is a side slope with a height of 85 m,where the entrance of the tunnel was planed to be opened. After talus materials were removed,there were two grouped high density formation cracks in direction of NS and NE. The two grouped cracks cut the rock stratum to form a unstable rock body.Thus,how to cut a tunnel under these geologic conditions i& a number one problem.

关 键 词:水电站 导流隧洞 洞脸边坡 结构面 处理 

分 类 号:TV551.12[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象