长河坝水电站工程特陡高边坡开挖施工技术  被引量:5

Excavation of High and Steep Slope for Changheba Hydropower Station

在线阅读下载全文

作  者:秦定龙[1] 田洪[2] 杨福蓉[2] 

机构地区:[1]四川电力职业技术学院,四川成都610072 [2]中国水利水电第五工程局有限公司,四川成都610066

出  处:《水力发电》2010年第11期32-34,共3页Water Power

摘  要:长河坝水电站工程是大渡河梯级开发中的第10级电站,大坝右岸以1 485 m高程为界分为坝肩开挖和基坑开挖,坝肩边坡最大开挖高程为1 791 m,最大开挖高度306 m(计算至1 485 m高程),开挖厚度15~40 m。右岸高边坡开挖施工条件复杂,经分析,按照钻孔、爆破和开挖甩渣分两个工序循环施工。目前长河坝电站工程右岸坝肩已开挖至坝顶1 697 m高程,工程进度和安全均处于可控状态。这表明施工场内交通布置、开挖施工程序(包括浅层支护、深层支护滞后开挖面高度)、爆破设计参数等的选择是合理、有效的,可供其他类似工程借鉴。The Changheba Hydropower Project is the tenth cascade development in Dadu River.The maximum excavation height of slope for right dam abutment is 306 m(from EL 1 485 m to 1 791 m) and the excavation thickness is 15-40 m.The excavation was cycle in accordance with two processes of drilling-blasting and excavation-dump.At present,the right abutment has been excavated to the elevation of 1 697 m and the progress and security are in control.The excavation shows the traffic layout,excavation process and blasting parameters choice are reasonable and effective.

关 键 词:长河坝 水电站工程 高边坡开挖 施工技术 Hydropower Station STEEP Slope 高程 右岸 大开挖 坝肩边坡 支护 梯级开发 施工条件 设计参数 可控状态 开挖高度 交通布置 基坑开挖 工程进度 爆破 

分 类 号:TV73[水利工程—水利水电工程] TM612[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象