机构地区:[1]甘肃省水利水电勘测设计研究院,甘肃兰州730000
出 处:《水力发电》2010年第11期60-63,共4页Water Power
摘 要:九甸峡水利枢纽工程混凝土面板堆石坝建在深厚覆盖层上,坝址处为不对称狭窄河谷,岸坡陡峭。在高陡岸坡处理、深厚覆盖层基础处理、高地震区抗震措施以及高寒、高海拔地区堆石坝施工技术等专题研究的基础上,对混凝土面板堆石坝、坝基开挖及基础处理以及坝基深覆盖层处理进行了设计,并对坝体稳定性及应力应变进行了分析。计算和观测数据分析表明,其成果满足规范要求,为深厚覆盖层及不对称狭窄河谷上建造高面板堆石坝的一次成功探索。The CFRD dam of Jiudianxia Water Project founds on deep overburden and the dam site locates on asymmetric narrow valley with steep slopes.After adopting the study results on slope treatment,deep overburden treatment,earthquake-resistance measure and CFRD dam construction technology in high-cold and high-altitude area,the CFRD dam,the dam foundation excavation and treatment and the deep overburden treatment were designed.The dam stability and the stress and strain were also numerically analyzed.The simulation and monitoring data analysis shows that the design meets the requirements of specifications and is a successful practices for constructing high CFRD dam on deep overburden and asymmetric narrow valley.
关 键 词:水利枢纽工程 混凝土面板堆石坝 坝设计 Dam Concrete Face 深厚覆盖层 狭窄河谷 基础处理 高面板堆石坝 不对称 高海拔地区 坝体稳定性 专题研究 应力应变 施工技术 深覆盖层 抗震措施 规范要求 观测数据 高陡岸坡
分 类 号:TV73[水利工程—水利水电工程] TM612[电气工程—电力系统及自动化]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.7