沉管隧道的一种最终接头形式及施工方法  被引量:7

A type of final joint of immersed tube tunnels and its construction method

在线阅读下载全文

作  者:肖晓春[1] 林家祥[1] 何拥军[1] 祝建伟[1] 

机构地区:[1]上海隧道工程股份有限公司,上海200080

出  处:《现代隧道技术》2005年第5期66-70,共5页Modern Tunnelling Technology

摘  要:最终接头是整个沉管隧道中的关键工序之一,干地施工法是最常用的一种最终接头施工方法。结合嘉兴电厂二期取水工程的具体特点,首次采用接头井的形式实现最终接头的干地施工。工程实践表明,结构的强度、刚度、稳定性、水密性均满足干地施工要求,大大降低了最终接头的施工风险,确保了施工质量。The final joint is a key structure for an immersed tube tunnel and it is often constructed under a dry condition. In accordance with the features of the water intake project of Jiaxing 2nd stage power plant, a unique type of joint well was employed to realize the dry condition construction for the final joint. Practice of the project indicated that the strength, stiffness, stability and watertightness of the final joint met the requirements of dry condition construction. The method also decreased the construction risk and ensured the construction quality.

关 键 词:沉管隧道 最终接头 钢封门 止水 

分 类 号:U455.46[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象