作 者:谢小平[1] 黄强[1] 徐晨光[2] 王义民[1] 赵麦换[3]
机构地区:[1]西安理工大学 [2]华北水利水电学院,郑州450008 [3]黄河勘测规划设计有限公司,郑州450003
出 处:《水力发电学报》2005年第6期6-8,29,共4页Journal of Hydroelectric Engineering
基 金:国家重点基础发展规划(973)项目(G1999043608);陕西省重点实验室项目(02JS37)
摘 要:通过分析公伯峡水电站施工度汛风险的影响因素,选定主要影响因素为龙羊峡水库入库的洪峰流量,对龙羊峡水库不同运行方式下公伯峡水电站的施工度汛方案,采用概率分布函数计算风险率法进行了风险分析。结果表明,在一定的汛初水位和汛限水位下,减少龙库百年一遇控泄流量,可降低公伯峡水电站的度汛风险。所选4种方案的风险率较为接近,可根据实际情况加以应用。In order to analyze the risk factors of flood handling schemes during construction period of Gongboxia Hydropower Station, the risk analysis methods are discussed and the factors which affect the flood handling during construction period of Gongboxia Hydropower Station are analyzed. The risk chief factor of flood handling during construction period of Gongboxia Hydropower Station is the peak flow to Longyangxia Reservoir. In this approach, a probability density distribution function is employed to calculate the risk ratio of different operation schemes of Longyangxia Reservoir. If the flow discharge to Longyangxia Reservoir is 100-year flood, the risk ratio of flood handling during construction period of Gongboxia Hydropower Station is decreased when the output discharge of Longyangxia Reservoir is reduced. The results show that the risk of these 4 schemes are similar, the best scheme can be selected for application according the actual conditions.
分 类 号:TV513[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.28