作 者:万建江[1]
机构地区:[1]新疆生产建设兵团第八建筑安装有限责任公司,新疆乌鲁木齐830054
出 处:《西部探矿工程》2006年第5期127-128,共2页West-China Exploration Engineering
摘 要:精河县下天吉水库导流、泄洪、排砂洞工程进口明渠右岸边坡开挖。施工钻具为4台KQJ100B型潜孔钻机,马道二层,每层高20m,按马道层数,一次造孔至马道高程,分层、分段往进口明渠内抛掷的施工方法。炸药为20岩石硝氨炸药,分段、导爆索、电雷管引爆。预裂后成果半孔率54%~78%,预裂面平整度不大于20cm,坡比与设计相符,预留马道平台保护层厚度平均60cm,边坡平整度符合规范要求。The right bank slope of entrance open ditch for a diversion, flood-discharge and draining sand tunnel project in Xiatianji reservoir of Jinghe county is excavated. The methods of construction are: four KQT100 B down-the-hole drills are used for drilling instruments; the packway consists two layers; the height of each layer is 20 m; oncethrough borehole making reaches packway's altitude; throwing in the direction of entrance open ditch, by layers and sectionally; No. 2 rock ammon-dynamite explosive is used with sectional detonating cord and electric detonator initiation. The achievements after pre-splitting are: half-borehole ratio ranges from 54% to 78%; flatness of pre-splitting face is not greater than 20 cm; the slope agrees with the value of design; the protective layer thickness of preplaced packway platform averages out 60 cm, the flatness of slope is up to the standard demand.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15