青藏铁路块石气冷结构路堤下冻土温度场变化分析  被引量:32

Analyses of the Temperature Fields within an Air Convective Embankment of Crushed Rock Structure along the Qinghai-Tibet Railway

在线阅读下载全文

作  者:马巍[1] 吴青柏[1] 程国栋[1] 

机构地区:[1]中国科学院寒区旱区环境与工程研究所冻土工程国家重点实验室,甘肃兰州730000

出  处:《冰川冻土》2006年第4期586-595,共10页Journal of Glaciology and Geocryology

基  金:国家重点基础研究发展规划项目(2002CB412704);中国科学院知识创新工程重大项目(KZCX1-SW-04);国家自然科学基金项目(4040101350534040)资助

摘  要:基于青藏铁路沿线多年冻土区温度监测断面, 选取了不同冻土分区中的8个块石路堤结构(块石路基、块石护坡、块石路基加块石护坡)断面, 对其下温度场的变化分析研究.结果表明: 经过2~3个冻融循环后, 块石结构路堤下冻土上限已抬升了1.4~5.3 m, 说明块石路堤结构已起到了积极调节下伏冻土温度的作用.结果也显示, 在上限抬升的同时, 其下部的冻土地温也在升高, 但是这种过程已逐渐被块石路堤结构的降温所抑制, 而这种抑制程度受控于不同的冻土区域.在不同的冻土分区中, 无论是何种形式的块石路堤结构, 其降温趋势是不同的. Ⅳ和Ⅲ冻土区块石路堤基底的负温积累比较明显, 而Ⅰ和Ⅱ区的较弱.On the base of in—situ monitoring the air convective embankment of crushed rock structure (included the crushed rock embankment, the embankment with crushed rock slope protection and the crushed rock embankment with crushed rock slope protection) along the Qinghai-Tibet Railway, eight monitoring profiles were chosen to analyze the change of ground temperature within an air convective embankment of crushed rock structure in permafrost region with different temperatures (Region I: Tcp≥-0. 5℃; Region Ⅱ: -1.0℃ ≤Tcp〈-0. 5℃; Region Ⅲ:-2.0℃≤Tcp〈-l.0 ℃; Region Ⅳ: Tcp〈-2.0 ℃, where, Tcp is the annual average ground temperature). After 2-3 freezing—thawing circles, the permafrost tables have risen 1.4-5.3 m, showing a positive effect of adjusting and cooling roadbed due to the building of the air convective embankment with crushed rock structure. Meanwhile, it is also revealed that the ground temperature below the permafrost table increases gradually at the initial stage of construction, along with the permafrost table rising. This process has been restrained by the air convective embankment with crushed rock structure. But the restraining effect is different from region to region, depending on temperature. The cooling effect of the air convective embankment with crushed rock structure in Regions Ⅲ and Ⅳ is stronger than that in Regions Ⅱ and Ⅰ.

关 键 词:青藏铁路 块石气冷路堤结构 多年冻土 温度场 

分 类 号:U213.14[交通运输工程—道路与铁道工程]

 