仁宗海水电站堆石坝坝基加固处理试验  被引量:1

Reinforcement Tests on the Mucky-soil Foundation of the Rockfill Dam for Renzonghai Hydropower Station

在线阅读下载全文

作  者:宋红英[1] 李晓力 

机构地区:[1]吉林大学,吉林长春130012 [2]北京振冲工程股份有限公司,北京100102

出  处:《水力发电》2006年第9期34-36,共3页Water Power

摘  要:仁宗海水电站坝基第7层灰色淤泥质壤土,呈可塑-软塑状,力学性质较差,承载力和变形模量低,不能满足基础承载、变形和坝坡稳定要求:地震烈度7度时为地震液化土。设计采用振冲碎石桩加固处理。试桩试验满足设计要求,为后期方案设计、施工提供了有效、可靠的参数。The 7th layer of the dam base of Renzonghai Hydropower Station is of grey mucky-soil, in a state of plastic to soft plastic and with poor mechanical properties, low load-carrying capacity and low deformation modulus. It cannot meet the requirements of load-carrying capacity of foundation, deformation and the stability of dam slope. It becomes liquefied soil when the earthquake intensity reaches 7. The detritus column vibroflotation is adopted to reinforce its foundation. The tests provide available credible data for the subsequent design and construction.

关 键 词:振冲加固 复合地基 施工工艺 堆石坝 仁宗海水电站 

分 类 号:TV223.22[水利工程—水工结构工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象