岭澳核电站硼回收系统除气器序列状态调试  被引量:1

State Commissioning of Gas Stripper Unit of Boron Recycling System of Ling’ao Nuclear Power Plant

在线阅读下载全文

作  者:李开锋 罗明坤[2] 李书周[3] 张文利[3] 

机构地区:[1]中广核工程有限公司,广东深圳518124 [2]中国核动力研究设计院,成都610041 [3]大亚湾核电运营管理有限责任公司,广东深圳518124

出  处:《核动力工程》2006年第6期87-90,102,共5页Nuclear Power Engineering

摘  要:对岭澳核电站硼回收系统除气器序列的功能和状态进行了描述;结合硼回收系统除气器序列的状态调试,给出了除气器序列状态调试的内容以及除气器序列按正常顺序从启动至停止时的部分状态参数曲线;针对状态调试过程中出现的具体问题,分析了产生的原因并提出了处理措施。结果表明,硼回收系统除气器序列状态运行完全满足系统设计要求。This paper describes the function and states of the gas stripper unit of boron recycling system of Ling'ao Nuclear Power Plant. Based on the states commissioning of the gas stripper unit of boron recycling system, this paper gives out the itmes in the states commissioning of gas stripper unit and parts of the state parameter curves of the gas stripper unit from starting-up to stopping according to the normal sequence. It aims at the problems appearing during states commissioning, analyzes the reason, and proposes the measures to handle the problems. The result indicates that states operation of gas stripper unit of boron recycling system fully satisfy the system design requirement.

关 键 词:除气器序列 调试 状态 

分 类 号:TL353[核科学技术—核技术及应用]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象