机构地区:[1]中国石油天然气管道局第二工程分公司,江苏徐州221008
出 处:《石油工程建设》2007年第1期36-38,共3页Petroleum Engineering Construction
摘 要:黑河是西部管道工程采用大开挖方式穿越的距离最长的河流,原油与成品油管道采用同沟敷设方式穿越该河流。文章介绍了穿越段的工程概况以及管道整体预制、管沟分层开挖、管道整体下沟和整体试压等一系列新的施工方法,该方法加快了施工进度,节约了施工费用。West Pipeline crossing Heihe River is the longest crossing project by a large excavation way and the method of laying both crude oil pipeline and products pipeline in a single trench. This paper depicts the engineering outline of the pipeline crossing project as well as a series of new construction methods such as integral pipeline prefabrication, trenching layer by layer, integral lowering pipeline into trench and integral pressure testing, which speed up the construction progress and reduce the construction cost.
关 键 词:原油管道 成品油管道 河流穿越 管道整体预制 管道整体试压
分 类 号:TE973.4[石油与天然气工程—石油机械设备]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.143