作 者:王楠[1] 白建华[1] 李友[2] 顾晓光[2] 李春山[2]
机构地区:[1]国网北京经济技术研究院,北京100761 [2]东北电网有限公司,辽宁沈阳110006
出 处:《中国电力》2007年第2期1-3,共3页Electric Power
摘 要:分析东北电网目前调峰存在的主要问题。根据东北电网电源现状及负荷需求预测,通过电力平衡及调峰平衡分析,从技术可行性角度,提出东北电网2020年抽水蓄能电站的最小建设规模。通过优化分析,从经济性角度,提出抽水蓄能电站的经济建设规模。两方案的对比分析结果为合理规划东北电网抽水蓄能电站提供参考。The main problems of peak regulation in northeast power gird were analyzed. Based on the current power installation and load forecasting, the minimal construction scale of pumped storage power plants (PSPP) in northeast power gird was proposed through power and peak balance analysis. Then the economical construction scale of PSPP was proposed through generation optimal analysis. Finally, the economical comparison of two PSPP construction plans provided valuable references for reasonable planning of PSPP in northeast power grid.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.3