摘 要:为提高航空项目工期估算的准确度,提出了基于改进的PERT的工期估算方法。针对经典PERT方法的不足,用莫尔法来确定重要活动的概率分布,用当量概率法对项目工期进行修正,进而减小经典PERT估算项目工期偏小的可能性。最后,结合某型飞机04段装配子项目为例介绍应用该方法进行工期估算的一般步骤。According to the authors' opinion, the traditional PERT needs to be improved because of its weakness. In order to increase the veracity of estimation of aeronautic project's duration, an estimation method based on improved-PERT is suggesed. The Monroe method and the equivalent-weight probability method are used to improve the traditional PERT, so as to amend the duration which is calculated by traditional PERT. The improved method is applied to estimate the project's duration of 04-segment assembly of a certain aviation project. Comparing with traditional PERT, the improved method can reduce the probability of project's duration lessening, and this just illustrates the effectiveness of the improved method.
分 类 号:TP391[自动化与计算机技术—计算机应用技术]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15