西龙池抽水蓄能电站压力钢管溶洞部位结构敏感性计算分析  被引量:1

Structural Sensitivity Calculation and Analysis of the Melt Hole Position of Steel Penstock of Xilongchi Pumped-storage Power Station

在线阅读下载全文

作  者:熊将[1] 杜英奎 王涛[2] 

机构地区:[1]北京国电水利电力工程有限公司,北京100024 [2]武汉大学水利水电学院,湖北武汉430072

出  处:《水力发电》2007年第10期70-73,共4页Water Power

摘  要:为了探讨溶洞对压力管道的影响,结合西龙池抽水蓄能电站实际工程,采用有限元方法对其进行了弹塑性有限元数值计算,并根据计算结果对溶洞大小、距离与压力管道最大主应力、最大位移以及稳定性之间关系进行了分析。研究结果表明:溶洞大小和距离对压力管道最大主应力和最大位移将产生明显的影响。In order to discuss the effect of melt hole on steel penstock and in combination with the practice of the Xilongchi Pumped-storage Power Station, the author adopts the elastoplastic FEM to make numerical calculation and analyzes the relationship between the size and distance of melt hole and the maximal principal stress and the maximal displacement and stability of steel penstock based on the results. The findings indicated that the maximal principal stress and the maximal displacement of steel penstock be influenced obviously by the size and distance of melt hole.

关 键 词:压力钢管 溶洞 有限元方法 敏感性分析 地质雷达 西龙池抽水蓄能电站 

分 类 号:TV732.4[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象