二滩拱坝施工期改变浇筑层厚度加快施工的分析  被引量:2

Analysis of Ertan Arch Dam Lift Thickness Variation During Construction Period for Speeding up Construction

在线阅读下载全文

作  者:陈秋华[1] 

机构地区:[1]中国水电顾问集团成都勘测设计研究院,四川成都610072

出  处:《水电站设计》2007年第4期14-16,共3页Design of Hydroelectric Power Station

摘  要:为保证二滩水电站按期发电,在二滩拱坝施工期,承包商提出了改变大坝混凝土浇筑层厚度加快施工进度的计划,即浇筑层厚度由1.5m改为3.0m,并以聚乙烯冷却水管代替钢管。本文分析了改变浇筑层厚度的可行性、温控条件,温度徐变应力。实践证明,加快施工进度的方案是成功的。n order to ensure that Ertan Hydropower Station generates power on time, during Ertan arch dam construction period,the contractor suggested to change the dam concrete lift thickness to speed up the construction progress,i, e. to change the lift thickness from 1.5m to 3.0m, and to use polyethylene cooling pipes instead of steel ones.In this paper feasibility of changing the lift thickness is studied,the temperature control conditions and temperature creep stresses are analysed. The construction practice demonstrates that the scheme for speeding up the construction is successful.

关 键 词:砼拱坝 砼浇筑 浇筑层厚度 冷却水管 温度 徐变应力 二滩拱坝 

分 类 号:TV544[水利工程—水利水电工程] TV642.4

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象