先简支后结构连续梁桥施工顺序分析  被引量:24

Study on Construction Orders of Simply Supported-Continuous System

在线阅读下载全文

作  者:麻文燕[1] 向中富[1] 陈善勤[1] 

机构地区:[1]重庆交通大学土木建筑学院,重庆400074

出  处:《重庆交通大学学报(自然科学版)》2007年第5期44-48,共5页Journal of Chongqing Jiaotong University(Natural Science)

摘  要:后浇结构层与梁端湿接头浇筑先后顺序以及二次负弯矩预应力筋张拉先后顺序是先简支后结构连续体系桥梁施工的关键工序.通过实例计算分析后浇结构层与梁端湿接头浇筑的先后顺序;同时,利用实例建立有限元模型分析二次负弯矩预应力张拉的先后顺序.通过对比分析,对预应力砼先简支后结构连续梁桥的受力、施工进行初步的探讨,以期更好的为工程服务.The constructing procedure of the monolithic layer and the wet joints of the girders and the orders of straining the pre-stress force are the key orders of the simply supported-continuous system. The orders of the monolithic layer and the wet joints of the girders are studied with practical project, and a limited element model was established to analyse the order of the wet joints of the girders and straining pre-stress force to the structure. Through the contrasting analysis, an elementary discussion of mechanics and construction was made towards the pre-stress simply supported-continuous system with the hope to better serve the project.

关 键 词:先简支后结构连续 湿接头 临时支座 整体化层 预应力张拉 

分 类 号:U445[建筑科学—桥梁与隧道工程] U443.15[交通运输工程—道路与铁道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象