220kV线路融冰方案的改进  被引量:22

Improvement on Ice-Melting Scheme for 220 kV Transmission Line

在线阅读下载全文

作  者:邓健 肖顺良 姚璞 郭正辉 吴小勇 贺伟明 

机构地区:[1]湘潭电业局,湖南省湘潭市411102

出  处:《电网技术》2008年第4期29-30,45,共3页Power System Technology

摘  要:2008年1月,湖南等南方省份发生了严重的冰雪灾害,220 kV线路覆冰严重。在此次冰雪灾害中,实施传统的高电压等级串多线路的220 kV线路融冰方案比较困难。文章对上述融冰方案在实际应用中遇到的问题进行了分析,针对这些问题提出了一种通过降低融冰电压等级对单一线路进行融冰的新的融冰方案。实际应用结果表明,采用新方案的融冰效果较好。In January, 2008 severe ice and snow disaster occurred in Hunan province and other southern and central provinces of China and this disaster made 220kV transmission lines seriously covered with ice, however, under such a severe disaster it was hard to adopt the traditional ice-melting scheme for 220kV lines, i.e., multi 220kV transmission lines are connected in series and the ending terminal of the final line is artificially three-phase short-circuited, then three-phase 110kV AC voltage is applied to the beginning terminal of the first line to make the ice melted by large short circuit current. For this reason, after the analysis on the problems encountered in applying above-mentioned ice-melting method to actual application, a new ice-melting scheme, namely using lower voltage class to implement ice-melting for single transmission line, was put forward. Practical application results show that the ice-melting effect of the proposed scheme is satisfied.

关 键 词:220 KV线路 覆冰 融冰 高电压技术 

分 类 号:TM852[电气工程—高电压与绝缘技术]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象