67m高3200t重钢结构人字塔架的安装  

Installation of 67m High and 3200t Steel Herringbone Tower

在线阅读下载全文

作  者:王卫东[1] 张玉林[1] 刘民[1] 高岩[1] 林勇明[1] 

机构地区:[1]中国建筑工程总公司,北京100026

出  处:《施工技术》2008年第5期100-104,共5页Construction Technology

摘  要:天津慈海桥摩天轮工程中,水上型钢箱柱体人字塔架截面大、高度高、质量大,吊装焊接施工困难。采用分段整体吊装、空中组焊的方法成功完成人字塔架安装,介绍了具体施工流程和安装施工中采取的主要措施。最后对塔架合拢后轮轴梁和塔顶位移进行监测。结果标明,位移精度满足要求,证明了该方法切实可行。Section steel box-column water herringbone tower was used in giant wheel of Tianjin Cihai Bridge. The herringbone tower is difficult to lift and weld because of its large cross section, high altitude and heavy weight. Integral multi-section lifting with high-altitude welding method was adopted to install herringbone tower. Construction process and measures were introduced. Displacement of axle wheel and top tower were monitored after the tower closure. The results show that the displacement can reach the requirements, and the installation method is feasible.

关 键 词:钢结构 塔架 分段吊装 施工技术 位移监测 

分 类 号:TU758.11[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象