伊川二电厂二期工程水源选择及供水方案设计  

WATER SOURCE SELECTION AND WATER SUPPLY PLAN OF POWER PLANT IN YICHUAN

在线阅读下载全文

作  者:葛喜坤 

机构地区:[1]河南省电力勘测设计院

出  处:《给水排水》1997年第10期27-30,共4页Water & Wastewater Engineering

摘  要:伊川二电厂二期工程补充用水259万m3/d,根据当地水文地质、水文气象及一期工程情况对二期工程供水方案进行了优化论证,决定采用水库渠调蓄库相结合的供水方案。The water supply facility for the 2nd phase project of The 2nd Power Plant in Yichuan, Henan province, was designed with total capacity of 25.9 thousand cubic meters per day. The plan of this project had been proved by experts for optimization according to the local hydrogeological and hydro meterological status and the practices of the lst phase project of this power plant and the water suuply scheme of water storage reservoir combined with regulating reservoirs had been adopted.

关 键 词:电厂补充水 水源选择 供水方式 优化 

分 类 号:TU991.4[建筑科学—市政工程]

 