超超临界1000MW机组汽动给水前置泵的安装优化  被引量:3

INSTALLATION OPTIMIZATION OF STEAM-DRIVEN FEED-WATER BOOSTER PUMP FOR ULTRA-SUPERCRITICAL 1000 MW UNIT

在线阅读下载全文

作  者:陈建县[1] 陶磊[1] 

机构地区:[1]国电北仑电厂,浙江宁波315800

出  处:《热力发电》2008年第9期68-70,74,共4页Thermal Power Generation

摘  要:对国电北仑第三发电有限公司(北仑电厂)超超临界1000MW机组汽动给水前置泵的安装位置从距主厂房零米改为17m运转层,并将一体式除氧器抬高至40.5m,提高了机组运行的经济性,改善了厂用电配电条件,减少了设备投资。此改动可为同类型机组的汽动给水前置泵设计、选型提供参考。The installed location of the steam- driven feed- water booster pump for ultra- supercritical 1 000 MW unit in Beilun Power Plant has been changed from elevation 0 m in the main machine hall onto 17 m operating floor,and the integrated mode deaerator Being heigtened to 10.5 m,thereby,the economic efficiency in operation of unit being enhanced, the distribution condition of service power being improved,and the invested capital of equipments being reduced. This modification can provide reference for design and type ,selection of steam - driven feed - water booster pump used for similar type of unit.

关 键 词:火电厂 超超临界 1000MW机组 汽动给水泵 前置泵 安装优化 

分 类 号:TK223.5[动力工程及工程热物理—动力机械及工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象