风/柴互补发电陆地并网调试  

Land Interconnected Commissioning of Wind/Diesel Complementary Power Generation

在线阅读下载全文

作  者:丁洪霞[1] 叶忠志[1] 舒伟[1] 

机构地区:[1]海洋石油工程股份有限公司,天津300452

出  处:《中国造船》2008年第A02期289-294,共6页Shipbuilding of China

摘  要:为了实现中国首台海上风力发电机与海上平台孤立电网的透平发电机组并网发电,用柴油机模拟电网,干式负荷模拟电网负荷进行陆地并网调试。详细阐述了陆地并网调试的过程和方法,分析了调试过程中风/柴的电参数变化,得出了满意的结果,对海上并网发电起到了一定的指导作用。In order to carry out the interconnected network generating electricity between the first offshore wind power generator and turbine generator of platform isolated power network, utilizing diesel generator simulates power network and using resistance and reactance simulates the load of the power network in erder to realize land interconnected commissioning. The means and aims of interconnected commissioning are described and the change of electricity parameters of wind/diesel generation is analyzed. The test result is very satisfied and the land test is guidable to sea interconnected network generating electricity.

关 键 词:风力发电 并网 模拟 

分 类 号:TM623[电气工程—电力系统及自动化] TP313[自动化与计算机技术—计算机软件与理论]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象