高层建筑板墙切割拆除工艺  被引量:2

The construction technology of cutting floor and wall in high-rise building

在线阅读下载全文

作  者:闫文斌 王宏林 章传学 

机构地区:[1]北京正邦兴业建筑技术开发有限公司,北京100083

出  处:《建筑结构》2010年第S2期654-656,共3页Building Structure

摘  要:因结构本身的复杂性,高层建筑斜坡面外墙、楼板切割及后期加固改造难度很大。通过对天津某实际工程的拆除工作,认为施工中应认真执行工艺标准,并通过现场实际调查,结合施工图纸,确定切割拆除顺序,编制可行性施工方案。在对上部结构有效支顶卸荷的前提下,按"楼板→次梁→主梁→柱"的顺序逐层、分段地安全切割拆除施工。Due to the complexity of the structure,the outer wall,floor of high-rise building on the slope surface was very difficult to cut and strengthen.The technology standards in construction should earnestly implement was determined.Through on-site an actual survey,combination of construction drawings,the order of cutting removals,construction scheme was prepared.On condition that the superstructure were practical supported and unloaded,in the order of floorsecondary beam-main beam – pillar,layer-by-layer and sector-by-sector to cut it in safety.

关 键 词:斜坡面外墙切割 有效支顶卸荷 先板后梁 切割详图 

分 类 号:TU746.5[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象