机构地区:[1]同济大学土木工程学院,上海200092 [2]上海市政工程设计研究总院,200092
出 处:《特种结构》2009年第2期101-104,共4页Special Structures
基 金:国家"十一五"科技支撑计划项目(2006BAJ16B07)
摘 要:以2010年上海世博会园区综合管廊工程为背景,对一个25m标准施工段内的预制预应力综合管廊和现浇整体式综合管廊的施工工期和土建成本等进行了分析与计算。结果表明,预制预应力综合管廊施工现场文明有序而整洁,具有良好的节能环保效益,总体经济性优于现浇整体式综合管廊。一个标准施工段内预制预应力综合管廊的施工工期比现浇整体式综合管廊减少约45%,土建成本降低约4%。According to the construction of municipal tunnel in 2010 Shanghai Expo Area, the construction period and the cost of precast prestressed municipal tunnel (PPMT) and cast in place municipal tunnel (CIPMT) of a 25 m construction section were calculated. Results showed that the general economic cost of the PPMT , with the advan- tages as environmentally friendly site operation and energy conservation, was lower than the CIPMT. The construction period and the cost of the PPMT of a 25m construction section were 45% and 4% lower than the CIPMT respectively.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.145