机构地区:[1]浙江省送变电工程公司,浙江省杭州市310016
出 处:《电网技术》2009年第10期74-77,共4页Power System Technology
摘 要:1000kV晋东南—南阳—荆门特高压交流试验示范工程是我国首个特高压输电工程,分裂导线架设中的牵张场布置是施工的重点与难点。文中详细介绍了如何进行1000kV交流输电线路8分裂导线并列同步牵引牵张场的选择、施工总平面策划和分区布置等安全技术,确保了工程安全顺利进行,可以为未来特高压交直流工程建设提供借鉴。The 1 000 kV power transmission pilot project from Southeast Shanxi via Nanyang is the first 1000 kV power transmission demonstration project in China. The arrangement of tugging and taking-up site for the stringing of 8-bundled conductor is an important and difficult problem in its construction. In this paper, how to choose the tugging and taking-up site, the drafting of general layout for the stringing and zoned schemes are presented in detail, this demonstration project to ensure the successfulness and security of the construction, and the experience from this construction is available for reference to UHVAC/DC projects in future.
分 类 号:TM72[电气工程—电力系统及自动化]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.147.52.13