作 者:武晓杰[1] 彭相国[2] 施召云[2] 佟阳[1]
机构地区:[1]中国水利水电第六工程局有限公司,辽宁丹东118002 [2]三峡大学土木水电学院,湖北宜昌443002
出 处:《施工技术》2009年第6期58-59,69,共3页Construction Technology
摘 要:溪洛渡水电站左岸1-3号导流洞进口闸门竖井混凝土施工由于受多种因素的影响,致使混凝土施工工期紧张。为加快施工进度,保证1-3号导流洞进口闸室按工期要求下闸,在混凝土浇筑施工过程中,采用免拆金属模板网以保证不同强度等级混凝土连续浇筑,减少模板支立、拆卸及混凝土面凿毛施工,不仅加快了施工进度,抢回了施工工期,还节约施工投入。Construction period of shaft concrete in left bank No. 1 to No. 3 diversion tunnel gate in Xiluodu Hydropower Station is very short because of many influence factors. To speeding up construction progress and guaranteeing lock chamber of No. 1 to No. 3 diversion tunnel entrance gate completed on time, non-removal metal mesh formwork is used to assure continuous pouring of different strength grade concrete, reduce standing and dismantling of formwork and chiseling concrete surface roughness during construction of concrete pouring. The use of non-removal metal mesh formwork not only improves construction progress but also saves construction cost.
分 类 号:TV73[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.3