110kV变电站雷电过电压的仿真研究  被引量:4

Simulation calculation of lightning overvoltage in 110kV substation

在线阅读下载全文

作  者:陈鸣辉[1] 何智强[2] 刘兴文[2] 周卫华[2] 毛文奇[2] 

机构地区:[1]湖南省电力公司永州电业局,湖南永州425000 [2]湖南省电力公司试验研究院,湖南长沙410007

出  处:《湖南电力》2009年第3期12-15,共4页Hunan Electric Power

摘  要:针对低压设备事故频繁发生的问题,使用电磁暂态计算程序ATP-EMTP(ATPDRAW)就某110 kV变电站雷击进线段杆塔塔顶落雷引起的过电压进行建模与仿真,通过建立系统中配电变压器、电源线、避雷器、接地系统等相关元器件的数学仿真模型,进行了雷击点、运行方式和杆塔接地电阻的比较,讨论了绝缘配合裕度计算等重要因素对雷电过电压的影响。Aiming at frequent faults existing in low voltage equipment, ATP - EMTP (ATPDRAW) was used to model and simulate overvoltage caused by lightning on the top of incoming transmission tower in one substation. Through establishing the digital simulation model of distribution transformers, power lines, attesters, grounding system, and relevant components, lightning points, operation modes, and tower grounding resistance were compared and the influence of important factors such as insulation corporation margin on lightning overvoltage were discussed.

关 键 词:雷电定位 过电压 计算 

分 类 号:TM86[电气工程—高电压与绝缘技术]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象