600MW空冷机组空冷岛的调试  被引量:4

COMMISION DEBUGGING OF AIR-COOLED ISLAND SYSTEMS FOR 600MW AIR-COOLED UNITS

在线阅读下载全文

作  者:杨海生[1] 李路江[1] 吴瑞涛[1] 刘春报 刘红霞 

机构地区:[1]河北省电力研究院,河北石家庄050021 [2]国电河北龙山发电有限责任公司,河北石家庄050021

出  处:《热力发电》2009年第7期66-68,71,共4页Thermal Power Generation

摘  要:对国电河北龙山发电有限公司2×600 MW空冷机组空冷岛的调试中出现的问题进行了分析,如冬季停机后起动空冷岛真空下降过快,全部空冷风机全负荷运转,汽封系统漏空气空冷岛背压急剧上升等,给出了调试中对上述问题采取的相关防范措施,并对调试中部分未能解决的问题,提出了具体建议。The problems appeared in commission debugging of the air- cooled island systems for two 600 MW air-cooled units of Guodian Longshan Power Generation Co Ltd,such as undue fast vacuum drop in air - cooled island during start - up of said units after their shutdown in winter, the rapid rise of back - pressure in said air - cooled isrand due to full - load operation of all cooling air fans and air - leakage in the steam seal system, etc. , have been analysed, and corresponding preventive measures adopted for above - mentioned problems in the commission debugging process being given; Regarding to a part of problems, which hadn't been solved in debugging,some concrete recommendations have been put forward.

关 键 词:600MW空冷机组 空冷岛 真空 空冷风机 背压 

分 类 号:TK264.1[动力工程及工程热物理—动力机械及工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象