检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
出 处:《建筑经济》2009年第8期90-92,共3页Construction Economy
摘 要:多因素影响下的工期索赔计算牵涉到三个重要问题:共同延误的索赔处理原则、网络计算的叠加和发散效应和时差的所有权。从共同延误的索赔处理原则入手,深入分析了网络计算叠加和发散效应产生的根本原因,探讨了时差所有权的归属问题。基于公平、简便和可操作性的考虑,提出了多因素影响下工期索赔计算的三个基本原则。Calculation of delay claims for project under muhifactor affection concerns about three important problems: principle of concurrent delay claims, piling up and effect-weakening of network calculation, ownership of float times. Starting from principle of concurrent delay claims, this paper analyzes the basic reason for piling up and effect-weakening of network calculation, and discusses about who owns float times. Concerning about justice, convenience, and practicality, this paper brings about three main principles of delay claims for project under multi-factor affection.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.28