石宝铁矿采场最终边坡稳定性FLAC模拟分析  被引量:5

The finally slope stability analysis based on FLAC numerical simulation for Shibao iron mine stope

在线阅读下载全文

作  者:张飞[1] 董辉[1] 陈世江[1] 

机构地区:[1]内蒙古科技大学,内蒙古包头014010

出  处:《中国矿业》2009年第10期100-102,共3页China Mining Magazine

摘  要:针对石宝露天铁矿三个采坑的采场最终边坡出现的不稳定现象,结合现场工程地质勘察和岩石力学试验,并运用有限差分法,使用FLAC数值模拟软件,对其进行了详细的分析和研究。通过研究,揭示了滑坡机理,对石宝露天铁矿采场最终边坡稳定性作出了客观评价,为露天矿下一步的工作方案、边坡监测方案和预裂爆破方案的制定,提供决策依据,对实际生产有着重要的指导意义。According to the instability phenomenon of the finally slope in Shibao open pit iron mine three mining pits stope. Combining site engineering geological exploration and rock mechanics test also using the finite difference method by FLAC numerical simulation software is made detailed analyze and research. Through the research, reveals the mechanism of landslide, making an objective evaluation about the finally slope stability of Shibao iron mine stope. Providing a basis for decision-making in the open pit iron mine' s next work on working scheme, slope monitoring scheme, Presplitting Blasting scheme. It has important guiding significance for the practice production.

关 键 词:矿山边坡 边坡稳定 FLAC 数值模拟 

分 类 号:TD824.7[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象