非洲加纳博恩电厂余热锅炉模块吊装  被引量:1

The HRSG Module Erection Work of the Kpone Power Plant,Ghana Africa

在线阅读下载全文

作  者:叶小桦 

机构地区:[1]广东火电工程总公司,广东广州510730

出  处:《重庆电力高等专科学校学报》2009年第3期13-17,共5页Journal of Chongqing Electric Power College

摘  要:针对余热锅炉垂直布置模块吊装工作中,因为该国现有吊机起吊能力不足,设计场地狭窄,无法采取原有配套的吊装工具和方案等问题,提出从侧面进行吊装的方法。对钢结构稳定性进行核算,改造其运输架进行吊装,满足吊装需求,提高了工作效率,显著降低施工费用。In the work of vertical arrangement of HRSG module hoisting,the Kpone Power Plant is unable to adopt old-style tools and planes of boiler module hoisting,because of the narrow working site and unavailability of enough capable cranes in Africa.The paper mainly discusses a mothod of module hoisting from sideway,which is based on the calculation of the steel structure stability and the transformation of transport planes to meet the hoisting demand.In this way,the working efficiency is raised and the construction charge is obviously reduced.

关 键 词:燃气-蒸汽联合循环发电厂 余热锅炉 模块吊装 

分 类 号:TK223.3[动力工程及工程热物理—动力机械及工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象