作 者:魏贤华[1]
机构地区:[1]中铁十四局集团有限公司广州分公司,广东广州511440
出 处:《桥梁建设》2009年第6期58-61,79,共5页Bridge Construction
摘 要:广深港铁路客运专线沙湾水道特大桥6号主墩双壁钢围堰设计嵌入水下岩层中7 m。6号墩双壁钢围堰采用圆形双薄壁钢壳和混凝土组合结构,结合6号墩双壁钢围堰的施工,介绍32.6 m大直径轻型双壁钢围堰结构设计、抗浮设计和水下岩层基坑开挖、双壁钢围堰制作、浮运、定位、下沉、封底、拆除等关键施工技术。该施工过程中采用的"先挖后沉"的施工工艺安全、可靠,大方量抓斗船开挖水下软质岩层快速、精确。The double-wall steel cofferdam for the main pier No. 6 of Shawan Water Course Bridge on Guangzhou-Shenzhen-Hong Kong Passenger Dedicated Railway is designed to be socketed 7 m into the rock stratum under water. The cofferdam used for the pier is a structure composited with round double thin wall steel shells and concrete. With reference to the construction of the cofferdam, the structural design of the 32. 6 m large diameter and lightweight double-wall steel cofferdam and the design of the anti-buoyancy of the cofferdam are presented, and the key construction techniques for excavating of the foundation pit for the cofferdam in the rock stratum under water, the manufacturing, floating, positioning, sinking, base sealing and dismantling of the cofferdam are described as well. In the construction of the cofferdam, the construction technology of "excavating first and sinking late" adopted for the cofferdam is safe and reliable and the excavating of the soft rock stratum under water by the large cubic grab barge is fast and accurate.
分 类 号:U443.162[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.145