布沼坝露天煤矿剥离工艺优化选择  被引量:8

Study on optimization selection of the stripping technology in Buzhaoba surface coal mine

在线阅读下载全文

作  者:杨宏[1,2] 才庆祥[1] 张天文 陈树召[1] 陈彦龙[1] 

机构地区:[1]中国矿业大学矿业工程学院,江苏徐州221116 [2]小龙潭矿务局,云南开远661601

出  处:《中国矿业》2010年第5期61-63,74,共4页China Mining Magazine

基  金:"十一五"国家科技支撑项目(2006BAB16B00)

摘  要:根据布沼坝露天煤矿五期扩建需要,分析了该矿的剥离工艺现状和开采条件,提出了五期扩建后可行的剥离工艺方案:表土剥离采用单斗-卡车间断工艺,泥灰岩剥离采用单斗-汽车间断工艺+一套轮斗连续工艺+卡车—破碎站半连续工艺的综合工艺,后期取消轮斗挖掘机连续工艺以简化剥离工艺系统布置。对布沼坝露天煤矿新增半连续工艺系统破碎设备进行比较研究,认为采用移动式破碎站不仅投资省,而且生产费用也较低。According to needs of the the stripping technology in fifth period extension of Buzhaoba surface mine,advancing doable the stripping technology projects by analysing stripping actuality and mining conditions when fifth period extension is finished.It is that topsoil stripped adopts shovel and truck technology,and marl is stripped with integrated process which are discontinuous mining system,BWE continuous system and crusher semi-continuous system,later predigest the stripping system by canceling BWE continuous system.By comparision crushing facility of semi-continuous technology system,it is not only lower investment but also reduce production cost if movable crusher is used.

关 键 词:露天煤矿 剥离 工艺优化 破碎站 

分 类 号:TD824.1[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象