检索规则说明:AND代表“并且”;OR代表“或者”;NOT代表“不包含”;(注意必须大写,运算符两边需空一格)
检 索 范 例 :范例一: (K=图书馆学 OR K=情报学) AND A=范并思 范例二:J=计算机应用与软件 AND (U=C++ OR U=Basic) NOT M=Visual
机构地区:[1]三峡大学水利与环境学院,湖北宜昌443002
出 处:《人民长江》2010年第10期27-29,共3页Yangtze River
摘 要:为了更好地研究面板堆石坝主、次堆石区分界线位置对坝体、面板的应力及位移的影响,结合水布垭面板堆石坝的设计资料,通过拟定主、次堆石区分界线分别位于坝轴线上游、下游及坝轴线3种方案,在竣工期(坝体施工完毕)和蓄水期(水库蓄水到正常水位)不同工况条件下,利用ANSYS的二次开发功能进行三维非线性应力应变分析计算,得到了3种方案的坝体应力、面板应力、坝体位移、面板位移及面板垂直缝、周边缝三向位移成果,通过对3种方案的计算成果进行比较分析,确定了主、次堆石区分界线位于坝轴线下游较为合理。In order to better investigate the effect of main,sub-rockfill zone boundary location of high concrete faced rockfill dam on stress and displacement of dam and slab,combining design data of Shuibuya Project,through drafting 3 schemes on the main,sub-rockfill zone boundaries which are located at upstream of dam axis,downstream of dam axis and dam axis respectively,and considering 2 working conditions,namely construction period(completion of dam construction) and the storage period(normal water level),we use ANSYS-APDL to conduct a 3-D non-linear stress-strain analysis for the Shuibuya Dam by Duncan E-B model.The analysis results of 3 schemes are obtained,including dam stress and displacement,slab stress and displacement,three direction displacements of slab vertical joints and peripheral joints,etc..Through comparison,we find the scheme that the boundaries are arranged at downstream of the dam axis is more reasonable.
关 键 词:主、次堆石区分界线 坝体应力位移 面板应力位移 接缝位移
分 类 号:TV641.43[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15