轻型井点降水施工技术  被引量:3

Construction Technique of Light Well Point Drainage

在线阅读下载全文

作  者:王为[1] 陈晓霞[1] 李雪松[1] 许洪伟[1] 

机构地区:[1]辽河油田分公司油田建设工程一公司,辽宁盘锦124010

出  处:《石油工程建设》2010年第3期130-131,共2页Petroleum Engineering Construction

摘  要:苏里格气田地处毛乌素沙漠深处,地下水位一般在-0.3m左右,地下多为流沙,拟建工程污水处理装置基础底标高都在-5.2m左右,明沟排水易引起流沙坍方,经研究决定采用轻型井点降水方案进行先降水后施工,采用真空泵或射流泵降水。文章对该降水方案的工作原理、施工工艺流程及操作要点、所用的材料与设备等进行了较为详细的论述,并指出该方案具有降水效果好,与深井井点降水方案相比费用较低等优点。Sulige Gas Field is located in deep Maowushu Desert where the water table is about-0.3 m and there are quicksand layers in foundation.Because the base bottom elevation of a planned waste water treatment facility is about-5.2 m,gutter drainage will easily cause collapse.Through investigation,the scheme of light well point drainage using vacuum pump or jet pump is adopted to lower water level prior to construction.The working principle of the light well point drainage method,its construction process and key operation points as well as materials and equipment needed are discussed in this paper.The scheme has the advantages such as good effect of lowering water level and reducing cost compared with the deep well point drainage scheme.

关 键 词:沙漠油田 基础施工 井点降水 施工工艺 

分 类 号:TU753[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象