一起线路保护改造中纵联保护与载波机接口配合问题的分析  被引量:4

Coordination between pilot protection and PLC interface in line protection reform

在线阅读下载全文

作  者:赵青春[1] 张道农[2] 罗克宇[2] 汪文全[3] 

机构地区:[1]南京南瑞继保电气有限公司,江苏南京211100 [2]北京国电华北电力工程有限公司,北京100120 [3]山西电力科学研究院,山西太原030001

出  处:《电力自动化设备》2010年第10期135-138,共4页Electric Power Automation Equipment

摘  要:针对一起线路保护改造中分相式纵联距离保护与载波机接口配合的问题,提出采用修改NSD550接收端内部逻辑的方法实现接口正确配合的解决方案。指出在设计时需详实考核继电保护与载波机的接口配合,特别是在线路改造时,既要更换线路保护设备,又要对应地调整通信接口设备或通信接口设备的使用方式,以避免线路投运后造成拒动或误动后果。此外,重申了纵联保护对载波通道传送延时的要求。For the incoordination between the phase-segregated distance pilot protection and the PLC interface in line protection reform,a solution is proposed to modify the inner logic of NSD550's receiving end. It is pointed that the interface coordination between protection and PLC should be considered carefully during protection design and line protection reform. Not only the line protections need to be replaced ,but also the corresponding communication interface equipment should be adjusted to prevent the improper operation of protections. The requirement of pilot protection for the transmission delay of PLC channel is emphasized.

关 键 词:线路保护 分相式纵联保护 传送延时 系统联调 配合 

分 类 号:TM773[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象