三峡三期工程施工提前方案实施及施工技术综述  

Summary on Phase III Construction Technology of the Three Gorges Project

在线阅读下载全文

作  者:曾明 

机构地区:[1]中国葛洲坝集团股份有限公司三峡分公司,湖北宜昌443134

出  处:《水力发电》2010年第2期5-9,共5页Water Power

摘  要:葛洲坝集团公司承担了三峡三期工程厂房坝段及电站厂房1B、2B两个标段的施工。为满足三期工程提前挡水、提前发电目标的实现,针对主要施工技术难点,采取了相应的解决方案。主要技术创新和工艺改进为:施工管理信息系统的开发应用,聚苯板保温材料的应用,制定混凝土施工预警制度,改进模板施工技术,改进廊道施工工艺和厂房大二期基坑回填、尾水扩散段施工技术,采用钢筋直螺纹连接工艺等等。Gezhouba Group undertakes the construction of the powerhouse dam and the powerhouse 1B and 2B of the third phase engineering of Three Gorges Project.In order to meet the requirements on early water storage and power generation,technical innovation and process improvement are taken,including the development and application of construction management information system,the application of polystyrene board for heat insulation,the development of warning system for concrete construction,the improvement of formwork construction technology,the improvement of gallery construction,the backfill of second phase foundation pit,the construction technology for tail water diffusion section and the use of straight thread connection technology for reinforcement bar.

关 键 词:三期工程 施工技术 三峡水利枢纽工程 

分 类 号:TV34[水利工程—水工结构工程] TU271.1[建筑科学—建筑设计及理论]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象