作 者:徐伯建
出 处:《价值工程》2011年第2期51-51,共1页Value Engineering
摘 要:对某500kV架空送电线路设计,线路全长29km,双回双分裂LGJ-630/45导线,地线一根采用GJ-100,另一根采用OPGW-120。在施工过程中,由于村民不同意该线路走向P13~P17段进行了2次改线。第1次改线,P13转角为右53°10′18″基础开始施工后由于遭到村民反对,经协调后进行了第2次改线,P13转角为右37°12′48″,以供参考。For a design of 500kV overhead transmission line, the length of line is 29kin, the wire is double back and double split LGJ-630/45 wire, one of ground line is GJ-100, the other one is OPGW-120. During the construction process, the villagers do not agree with the line towards P13 N P17 segment, so the lines are changed two times. The first change is that the corner of P13 is changed into the right 53°10′18″, which is opposed by the villagers after the basic construction, so they coordinated the second times change which is that the corner of P13 is changed into the right 37°12′48″or reference.
分 类 号:TM7[电气工程—电力系统及自动化]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.198