济钢3200m^3高炉开炉实践  

Blowing-in Practice of 3200m^3 Blast Furnace in Jinan Steel

在线阅读下载全文

作  者:韩俊杰[1] 李丙来[1] 董龙果[1] 张殿志[1] 

机构地区:[1]济钢集团有限公司,山东济南250101

出  处:《山东冶金》2011年第1期12-14,共3页Shandong Metallurgy

摘  要:由于烘炉方案合理、参数控制严格,济钢3200m3高炉10d完成了烘炉,并进行了打压查漏,消除了事故隐患。开炉方案制定精确,通过控制送风节奏、及时调整装料制度,开炉后炉温合适,加风顺利,炉况顺行,3天喷煤,5天达产。Because of drying out scheme in reason and strict control of the parameters,Jinan Steel's 3 200 m3 BF drying out was done in ten days.The leak checking and the leak treating were made by pressure,eliminating accident potential.By establishing precise starting-up program,controlling the rhythm of the air supply and adjusting charging system in time,the furnace temperature was right after blowing-in,adding wind was well-off and the furnace operated regularly,realizing coal injection in 3 days and attaining designed capacity in 5 days.

关 键 词:高炉 烘炉 开炉操作 装料制度 

分 类 号:TF542.5[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象